估算交付日期

标准交付时间

In order to define the delivery time, you have to know three things:

  • Customer Lead Time :

    That is the time you promise to your customer for a delivery. It corresponds to the average delay between the confirmation of the customer order and the delivery of the finished goods. It can be defined in the product form, in the Procurement and Locations tab.

    This time will be influenced by the Manufacturing Lead Time and the Delivery Lead Time.

  • Manufacturing Lead Time :

    This is the time you need to produce one unit of a product. If this product needs other sub-products, the different manufacturing times will be summed. It can also be defined in the product form, in the Procurement and Locations tab.

  • Delivery Lead Time :

    This is the time your supplier needs to deliver the goods. This delay can be defined in the product form in the Suppliers tab.

For example, if we have to deliver some products to a customer in a month (in 30 days). You promise to deliver the goods to the customer within 10 days, the manufacturing time is equal to 4 days and our suppliers deliver the raw materials within 3 days.

According to those numbers, we will have to start the process in 23 days if we have to order raw materials.

依据MRP1规则的定期物流

MRP是基于软件的生产,计划和库存控制系统,被用作管理生产流程。

It is a computer-based system in which the given Master Schedule is exploded with Bills Of Material, into the required amount of raw material, parts and subassemblies needed to produce the final products in each period.