Project Quotas
KubeSphere uses Kubernetes requests and limits to control resource (for example, CPU and memory) usage in a project, also known as resource quotas in Kubernetes. Requests make sure a project can get the resources it needs as they are specifically guaranteed and reserved. On the contrary, limits ensure that a project can never use resources above a certain value.
Besides CPU and memory, you can also set resource quotas for other objects separately such as Pods, Deployments, Jobs, Services, and ConfigMaps in a project.
This tutorial demonstrates how to configure quotas for a project.
Prerequisites
You have an available workspace, a project and a user (ws-admin
). The user must have the admin
role at the workspace level. For more information, see Create Workspaces, Projects, Users and Roles.
Note
If you use the user project-admin
(a user of the admin
role at the project level), you can set project quotas as well for a new project (i.e. its quotas remain unset). However, project-admin
cannot change project quotas once they are set. Generally, it is the responsibility of ws-admin
to set limits and requests for a project. project-admin
is responsible for setting limit ranges for containers in a project.
Set Project Quotas
Log in to the console as
ws-admin
and go to a project. On the Overview page, you can see project quotas remain unset if the project is newly created. Click Edit Quotas to configure quotas.In the displayed dialog box, you can see that KubeSphere does not set any requests or limits for a project by default. To set limits to control CPU and memory resources, use the slider to move to a desired value or enter numbers directly. Leaving a field blank means you do not set any requests or limits.
Note
The limit can never be lower than the request.
To set quotas for other resources, click Add under Project Resource Quotas, and then select a resource or enter a recource name and set a quota.
Click OK to finish setting quotas.
Go to Basic Information in Project Settings, and you can see all resource quotas for the project.
To change project quotas, click Edit Project on the Basic Information page and select Edit Project Quotas.
Note
For a multi-cluster project, the option Edit Project Quotas does not display in the Manage Project drop-down menu. To set quotas for a multi-cluster project, go to Projects Quotas under Project Settings and click Edit Quotas. Note that as a multi-cluster project runs across clusters, you can set resource quotas on different clusters separately.
Change project quotas in the dialog that appears and click OK.